Ep. 033 - 300 Data Center Bans, 3 Projects Delayed: Moratoriums Explained (Datacenter, Energy)

Maya BarkinReyk KnühtsenJordan NanosJeremie Eliahou Ontiveros

SemisEnergyPolicy
YouTube ↗
TL;DR
  • The headline number and the tradeable number are two different universes: 300+ data center moratoriums are enacted across the US right now, yet SemiAnalysis's project-level mapping finds only three projects actively affected. Maya Barkin's database tracks 400+ local instruments across 17 states against a ~3,500-entry US pipeline; the first screen caught 77 campuses above 20MW (~20GW) inside restricted jurisdictions, and 74 of them fell out on closer inspection — "only three remained... that's 7.6% of what is inside a restricted boundary": an AWS project near Commercial Point, Ohio, the NorthPoint campus in Pennsylvania, and a CoreSite expansion in Colorado.
  • Roughly 80% of live restrictions have zero capacity behind them — these are overwhelmingly preemptive ordinances by towns "legislating before a project exists." A delay requires many things to be true simultaneously: the instrument must reach the parcel (county moratoriums cover only unincorporated territory), overlap the project timeline, cover the use, and hit a project that still needs the gated approval, with no carve-out or viable redesign path. The project must also still be active — not canceled, withdrawn, or delayed for another reason — and "that doesn't happen that often actually."
  • Jeremie's market call from Bangkok: the moratorium wave doesn't move the SemiAnalysis forecast, and it's actively making behind-the-meter the premium configuration. The market is entering "a moment of oversupply of early-stage projects," so canceled or speculative sites were never in the base case; meanwhile the Greg Abbott/ERCOT pushback means grid-connected sites are "scarce and now increasingly risky whereas behind-the-meter sites are not scarce." The red line to watch is a material state-level moratorium that blocks even off-grid projects — "if that were to happen in Texas... at that scale," the thesis changes. Jordan noted that a moratorium passed legislatively would differ from a revocable executive order.
  • New York's first-ever statewide moratorium — pausing environmental permits for 50MW+ data centers until July 2027 — touches ~1.4GW of planned capacity, all 2028 or later, and delays roughly 800MW by 6–10 months. In the TeraWulf discussion, the project's drift to 2029 in investor documents was treated as distant enough not to affect the near-term view: "it's 2029, right? That's a century away for me. I only know the next 12 to 18 months."
  • The politics are cheap signaling into November, and it cuts across party lines. SemiAnalysis's electorate poll found that some respondents were net positive on AI while net negative on data centers — the objections were power first, water second, not simply AI anxiety — making moratoriums "very cheap political positioning" ("I just put out this moratorium, it's not actually doing anything, but... I'm anti-data center just as much as you guys"). Executive orders that bypass the legislature can be controlled and revoked by governors.
  • The circumvention playbook is real: SpaceX pushed a deannexation of its 444-acre Brownsville parcel — through what Reyk recalled as a six-hour Saturday town hall amid protests — moving it into Cameron County days before Brownsville enacted its moratorium. "Oh, I'm not in your jurisdiction anymore. You can't get me." Other routes: relocate, redesign, litigate, or buy land with entitlements already in place rather than greenfield land needing rezoning.
  • The beneficiaries: behind-the-meter developers with power already secured, plus on-site generation and gas midstream — "turbines, gensets." The Texas audit only touches ERCOT-queue projects, so fully islanded campuses sit outside its scope; Reyk expects developers "dealing with the ERCOT uncertainty craziness" to switch to BTM: "I'm just going to go ahead and find a gas pipeline and call it a day."
Digest · the substance, structured for research

1. 300 moratoria, 3 affected projects: the mapping nobody else did

  • Maya's definition to anchor the episode: a moratorium is "a temporary legal pause," usually local, that "halts approval, permitting and construction of new data centers" — almost always a freeze on new applications, not existing facilities, lasting months to a year and often revoked or replaced. Governments use them because zoning codes predate "100-plus megawatt to multiple gigawatt" facilities, and because a pause is "a quite low-cost way for elected officials to answer local opposition."
  • Her methodology, which is the note's core edge: most observers "were counting these moratoriums but were not mapping them onto the data center sites." She built a database of 400+ local instruments across 17 states — tracked through the full lifecycle from proposed to enacted, rejected, expired, or lifted, including permanent zoning bans — and tested each against a ~3,500-entry US project pipeline.
  • Two screens: campuses above 20MW inside restricted jurisdictions gave 77 campuses (~20GW); checking each for legal reach, carve-outs, permits already in hand, and timeline overlap eliminated 74. Only three projects remain actively affected in the mapping: an AWS project near Commercial Point, Ohio, NorthPoint in Pennsylvania, and a CoreSite expansion in Colorado.
  • Why so few: "around 80% of live restrictions have no capacity at all" — towns legislating before a project exists or after a campus is already approved. Jordan's incredulous restatement stands as the episode's headline: everything on the chart is actively affecting three projects.

2. Jeremie's forecast: moratoriums are a gift to behind-the-meter

  • Calling in from Bangkok, Jeremie's framing: "we're starting to get into a moment of oversupply of early-stage projects," and SemiAnalysis doesn't count these as delays because affected sites "were never projects that would have a material impact the way we forecast the market" — permits, filings, and physical evidence were absent.
  • The second-order effect is the tradeable one: the Abbott letter's logic — grid connection risks residents' power prices, off-grid doesn't — means "if you bring your own power... there's no risk whatsoever that power prices go up because of you," making BTM "an easier or more derisked project." Options with gas and land in West Texas and elsewhere are increasing; "grid-connected sites are scarce and now increasingly risky whereas behind-the-meter sites are not scarce."
  • His stated worry condition: a material state-level moratorium blocking even off-grid projects — New York-style restrictions at Texas scale. "If that were to happen... we would probably be —" but "for now, we're fine essentially." Jordan added that a legislated moratorium would differ fundamentally from a governor's revocable executive order.

3. The conjunction test — and the SpaceX deannexation maneuver

  • Maya's full test for an actual delay: the instrument must reach the parcel (county moratoriums apply only to unincorporated territory, so a campus inside an incorporated city escapes), be enacted and still in force, overlap the project timeline — not too early, not "a 3-to-6-month pause that expires years before a project planned for 2028" — cover the use and megawatt threshold, gate an approval the developer still needs, resist redesign, and have no carve-out. The project must remain active rather than canceled, withdrawn, or delayed for another reason. Federal land, federal approvals, or other pre-existing rights can provide a separate permitting pathway.
  • Reyk's specimen of "watching somebody weasel out of it": SpaceX pushed deannexation of its 444-acre parcel from Brownsville's jurisdiction through what he recalled as a rushed six-hour Saturday town hall amid protests, landing it back in Cameron County — which has no moratorium — days before Brownsville enacted its own. "Now they're safe to build whatever they want there. And some of our subscribers know what they're building there." Right next to Starbase.

4. BANANAs, beehives, and cheap election-season signaling

  • The top four states — Michigan, Ohio, North Carolina, Georgia — hold roughly half of local instruments, clustering where buildout has been fastest. Michigan has 45 enacted, with the surge triggered by the data center tax exemption the governor signed in late 2024 — "yet we see no pipeline exposure."
  • Maya's polling finding, the episode's most counterintuitive data point: the poll found some respondents net positive on AI while net negative on data centers — "very odd if you thought data centers were this physical manifestation of AI anxiety." Cited concerns were power first, water second. That makes anti-data-center posturing "a really good point to harp on" through November, and Maya notes it now "cuts across party lines."
  • The uninformed-electorate specimen: Lambda's CEO Stephen/Steven Bibin replied to a "not in my backyard" critic on X that the building the critic circled "is actually Stream Data Centers' Minneapolis 2 site" — the person already lived beside one unknowingly.
  • The field-research color is worth the listen alone: county meeting minutes, Instagram reels, and "on the right anti-data-center Facebook group you'll get the entire project layout and plan" from photographed poster boards. The meeting-room read was that "everybody hates these" and the pushback can be overwhelming — not "make it smaller" but "not here, go somewhere else." Reyk's uncle's acronym upgrades NIMBY to BANANA: "build absolutely nothing anywhere near anyone." Maya says opposition is not usually asking for a smaller project or more community benefits; it is demanding that the project go away.
  • Jeremie says community-benefit packages — schools, roads, and other infrastructure — are not working because they do not address environmental and noise concerns at the root. Maya agrees, while Reyk notes that hyperscalers have long tried such measures, including tree planting, water infrastructure, and even Amazon's rooftop beehive.

5. State regimes diverge — and BTM plus gas midstream win

  • New York, the first statewide moratorium in the US, pauses state environmental permits for 50MW+ data centers until July 2027 while a generic environmental impact statement is written: ~1.4GW touched, all 2028+, ~800MW delayed 6–10 months. Stream Data Centers is the only affected project with an application actually pending; the rest were pre-application.
  • Pennsylvania and Oregon faced the same pressure but stopped short: Pennsylvania's "conditional permitting regime" makes DEP hold applications until requirements and local approval are met, pulls data centers from fast-track permitting, and prohibits NDAs — "it slows unvetted projects but doesn't stop vetted ones." Oregon merely paused projects on state-owned land for a year, with no impact on the forecast.
  • The discussion said many hyperscalers use NDAs with local governments, which can make citizens find out about a data center very late in the process. An AWS Ireland example was recalled tentatively as a blow-up. Jordan called putting city council members under NDA "so they can't tell the citizens they represent what's going on" silly; the discussion also noted lawsuits on both sides.
  • Closing advice for developers, half-joking: pull a SpaceX and "create your own town," go to unincorporated middle-of-nowhere Texas, buy land with existing approvals and entitlements, or litigate if the case is strong. Maya's broader point is that projects usually relocate, get reshaped, or face litigation rather than simply disappear. Final beneficiary call: BTM operators with secured power, fully islanded campuses outside the Texas audit's ERCOT-queue scope, and "on-site generation and gas midstream — turbines, gensets."